A line's tasks total 40 minutes of work per unit and the cycle time is 6 minutes. Precedence constraints force the planner to use 8 stations. What is the line efficiency, and how does it compare with the theoretical minimum number of stations?
- A. About 83.3%; the theoretical minimum is 8 stations
- B. About 95.2%; the theoretical minimum is 7 stations
- C. About 66.7%; the theoretical minimum is 6 stations
- D. About 83.3%; the theoretical minimum is 7 stations
Correct answer: D. About 83.3%; the theoretical minimum is 7 stations
Efficiency = work content ÷ (stations × cycle time) = 40/(8 × 6) ≈ 83.3%. Minimum stations = ⌈40/6⌉ = ⌈6.67⌉ = 7, so precedence costs one extra station. 95.2% would be the efficiency with 7 stations.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- What does =DATE(2028,3,1) - DATE(2028,2,1) return in Excel (with the result formatted as a number)?
- Payoffs (₹ lakh) for three acts under three equally uncertain states: A: 50, 20, 10; B: 30, 30, 30; C: 70, 0, 5. Which act is chosen under…
- A pump fails at random with a mean time between failures of 500 hours, and each failure is repaired instantly. What is the probability of…
- A distributor ships 500 units a day from a port to its warehouse, and goods spend 12 days on the road. Each unit is worth ₹2,000 and…
- A firm's inventory turnover (COGS ÷ average inventory at cost) is 8 a year, and it targets 12 without any change in COGS of ₹96 crore…
- A gauge study on a shaft diameter finds a total observed standard deviation of 5 µm, of which the repeatability-and-reproducibility…