A line's tasks total 40 minutes of work per unit and the cycle time is 6 minutes. Precedence constraints force the planner to use 8 stations. What is the line efficiency, and how does it compare with the theoretical minimum number of stations?

  1. A. About 83.3%; the theoretical minimum is 8 stations
  2. B. About 95.2%; the theoretical minimum is 7 stations
  3. C. About 66.7%; the theoretical minimum is 6 stations
  4. D. About 83.3%; the theoretical minimum is 7 stations

Correct answer: D. About 83.3%; the theoretical minimum is 7 stations

Efficiency = work content ÷ (stations × cycle time) = 40/(8 × 6) ≈ 83.3%. Minimum stations = ⌈40/6⌉ = ⌈6.67⌉ = 7, so precedence costs one extra station. 95.2% would be the efficiency with 7 stations.