Management & CommerceHardOperations · project management · MBA placement

A project has a budget at completion of ₹200 lakh. To date, earned value is ₹90 lakh and actual cost is ₹100 lakh. What cost performance index must the remaining work achieve to finish exactly on the original budget (TCPI based on BAC)?

  1. A. 0.90
  2. B. 1.11
  3. C. 1.22
  4. D. 1.10

Correct answer: D. 1.10

TCPI = (BAC − EV)/(BAC − AC) = (200 − 90)/(200 − 100) = 1.10: every remaining rupee must deliver ₹1.10 of work. 0.90 is the current CPI and 1.11 is its reciprocal.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic