A project has a budget at completion of ₹200 lakh. To date, earned value is ₹90 lakh and actual cost is ₹100 lakh. What cost performance index must the remaining work achieve to finish exactly on the original budget (TCPI based on BAC)?
- A. 0.90
- B. 1.11
- C. 1.22
- D. 1.10
Correct answer: D. 1.10
TCPI = (BAC − EV)/(BAC − AC) = (200 − 90)/(200 − 100) = 1.10: every remaining rupee must deliver ₹1.10 of work. 0.90 is the current CPI and 1.11 is its reciprocal.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A churn model has an ROC AUC of 0.80. What is the most accurate interpretation?
- A bank mails 50,000 customers, of whom 2,000 respond. When customers are ranked by a model's score, the top 10% (5,000 customers) contain…
- Base year: product A, price ₹10, quantity 20; product B, price ₹5, quantity 40. Current year: A, price ₹12, quantity 15; B, price ₹10…
- A linear regression of weekly units sold on price gives a slope of −20 units per rupee. The average price is ₹15 and average weekly sales…
- A maker of electronic controllers sees many failures in the first weeks of use, very few for several years, and then a rising failure rate…
- An LP maximises Z = c₁x + 4y subject to 2x + y ≤ 16, x + 2y ≤ 14 and x, y ≥ 0. With c₁ = 3 the optimum is at (6, 4). Over what range of c₁…