In Kraljic's purchasing portfolio matrix, a component with low profit impact but high supply risk (one specialised supplier, hard to substitute) falls in which quadrant, and what strategy suits it?
- A. Bottleneck item; secure supply via buffer stock or alternative sources
- B. Leverage item; use competitive bidding among many suppliers to cut price
- C. Strategic item; build a deep partnership with joint development
- D. Non-critical item; simplify and automate buying to cut order costs
Correct answer: A. Bottleneck item; secure supply via buffer stock or alternative sources
Kraljic classifies items by profit impact and supply risk. Low impact with high risk is a bottleneck item, where the priority is assuring supply, not saving money. Leverage items are high impact, low risk.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A buyer in Pune imports machinery from Germany. Under Incoterms, which statement correctly contrasts EXW (Ex Works) with DDP (Delivered…
- Two managers rank five suppliers (1 = best). Manager X: S1 1, S2 2, S3 3, S4 4, S5 5. Manager Y: S1 2, S2 1, S3 4, S4 3, S5 5. What is…
- A u-chart tracks defects per unit of fabric rolls. The average is ū = 0.5 defects per unit, and each sample inspects 8 units. What are the…
- A filling line's mean drifts upward by about half a standard deviation and stays there. A standard Shewhart X̄ chart with 3-sigma limits…
- Table ord(cust, day) has rows (A, 1), (A, 5), (A, 12), (B, 3), (B, 4). What does this query return? SELECT AVG(gap) FROM (SELECT LEAD(day)…
- cust has rows (1, Asha), (2, Ravi), (3, Meena). ord(oid, cid, status) has (10, 1, 'paid'), (11, 1, 'due'), (12, 2, 'due'). How many rows…