Management & CommerceHardOperations research · MBA placement
A firm wants to lay fibre linking five sites at minimum total cable length. Possible links (km): A–B 4, A–C 3, B–C 2, B–D 5, C–D 7, C–E 8, D–E 6, A–E 9. What is the minimum total length that connects all sites?
- A. 14 km
- B. 16 km
- C. 18 km
- D. 20 km
Correct answer: B. 16 km
Kruskal's method picks B–C 2, A–C 3, skips A–B 4 (it would close a loop), then B–D 5 and D–E 6: total 16 km. 14 km adds the four cheapest links including the loop, and 20 km is the star from C.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Pipelines (capacity in kilolitres per hour): Source→A 10, Source→B 8, A→B 2, A→Sink 6, B→Sink 9. What is the maximum flow from Source to…
- A van leaves depot D, visits A, B, C and E once each and returns. Distances (km): D–A 30, D–B 19, D–C 18, D–E 17, A–B 15, A–C 22, A–E 23…
- A sales regression has strongly autocorrelated residuals: each month's error tends to have the same sign as the last. What value of the…
- A regression predicts store sales from advertising (₹ lakh) and footfall (thousands). The raw coefficients are 4.0 for advertising and 0.5…
- In a demand model, regressing the predictor 'price' on all the other predictors gives R² = 0.90. What is the variance inflation factor…
- Two identical pumps run in active parallel, and the system works as long as at least one works. Each pump fails at a constant rate with an…