Management & CommerceModerateOperations · capacity · MBA placement
A cement company adds a new kiln only after demand has clearly exceeded current capacity for some time, accepting some lost sales to keep utilisation high. Which capacity strategy is this?
- A. Lead strategy
- B. Lag strategy
- C. Match (tracking) strategy
- D. Chase strategy
Correct answer: B. Lag strategy
A lag strategy adds capacity after demand has grown, maximising utilisation and cutting risk but losing some sales. A lead strategy builds ahead of demand, and match adds small increments as demand moves.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Goldratt's five focusing steps of the Theory of Constraints are listed out of order: P. Elevate the constraint Q. Subordinate everything…
- A warehouse cycle-counts its 2,000 SKUs by ABC class: 100 A items are counted monthly, 300 B items quarterly and 1,600 C items once a…
- A single-server passport-verification desk (M/M/1) receives 9 applicants an hour and serves 12 an hour. What is the probability that at…
- At an M/M/1 service counter, customers arrive at 10 an hour and are served at 12 an hour. What is the probability that an arriving…
- In an M/M/1 queue with λ = 8 and μ = 10 per hour, the average queue length (Lq) is 3.2. What is the average length of the queue…
- Patients arrive at a clinic at 8 an hour (Poisson) and pass first through registration (one clerk, exponential service at 10 an hour) and…