Management & CommerceModerateMBA placement (Operations)
A CONWIP line releases a new job only when a finished job leaves. Its throughput is 150 jobs a day and management wants an average flow time of 2 days. At what level should the WIP cap be set?
- A. 75 jobs
- B. 152 jobs
- C. 300 jobs
- D. 450 jobs
Correct answer: C. 300 jobs
By Little's law WIP = throughput × flow time = 150 × 2 = 300 jobs. Capping WIP there holds flow time at about 2 days as long as throughput stays at 150 a day; 75 divides instead of multiplying.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A lot of 20 printed circuit boards contains exactly 3 defective boards. A buyer inspects 4 boards chosen at random without replacement…
- A one-way ANOVA compares weekly sales under 3 store layouts with 10 stores each. The between-groups sum of squares is 120 and the…
- A logistic regression for loan default gives log-odds = −3 + 0.8 × (number of missed payments). For an applicant with 5 missed payments…
- A telecom churn model scores 97% accuracy on a hold-out sample, but fails in live use. Investigation shows one input was 'number of days…
- An analyst fits a demand model with 40 candidate predictors, many of them irrelevant, and wants regularisation that can drive some…
- An A/B test was designed to split 10,000 visitors 50/50, but the logs show 5,200 in control and 4,800 in treatment. What is the right…