A CONWIP line releases a new job only when a finished job leaves. Its throughput is 150 jobs a day and management wants an average flow time of 2 days. At what level should the WIP cap be set?

  1. A. 75 jobs
  2. B. 152 jobs
  3. C. 300 jobs
  4. D. 450 jobs

Correct answer: C. 300 jobs

By Little's law WIP = throughput × flow time = 150 × 2 = 300 jobs. Capping WIP there holds flow time at about 2 days as long as throughput stays at 150 a day; 75 divides instead of multiplying.