A plant uses the run-out-time method to choose its next production run. Items (stock; weekly demand): A (300; 50), B (200; 40), C (120; 40), D (100; 20). Which item should be produced next?
- A. D, as it has the lowest stock
- B. C, as it runs out soonest
- C. A, as it has the highest demand
- D. B, as it has the median run-out
Correct answer: B. C, as it runs out soonest
Run-out time = stock ÷ demand: A 6, B 5, C 3, D 5 weeks. C runs out first, so it is scheduled next even though D has less stock on hand.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Order values have mean ₹520, median ₹480 and standard deviation ₹80. What is Pearson's second coefficient of skewness?
- Individual order values have mean ₹500 and standard deviation ₹120. For a random sample of 36 orders, what is the probability that the…
- A decision-tree node holds 10 customers: 6 renew and 4 do not. A split sends 5 customers (all renewers) left and 5 customers (1 renewer, 4…
- For the same split (parent 6 renew / 4 not; left child 5/0; right child 1/4), what is the information gain using entropy in bits (to two…
- A fraud model is tested on 1,000 transactions: it flags 130, of which 40 are truly fraudulent; 10 frauds are missed; 860 genuine…
- B1:E1 hold sales thresholds 0, 1000, 5000, 10000 (ascending) and B2:E2 hold commission rates 0%, 5%, 8%, 10%. What do =HLOOKUP(7500…