Management & CommerceHardMBA placement (Operations) · UGC NET Management
A pilot work-sampling study suggests machines are idle 20% of the time. How many random observations are needed to estimate the idle share within ±2 percentage points at 95% confidence?
- A. 384
- B. 1,537
- C. 1,600
- D. 2,401
Correct answer: B. 1,537
n = z²p(1 − p) ÷ e² = 1.96² × 0.2 × 0.8 ÷ 0.02² ≈ 1,536.6, so 1,537 observations. 2,401 uses the conservative p = 0.5, and 1,600 uses z = 2.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A time study records an average observed time of 2.0 minutes for an element, the operator is rated at 110%, and allowances are 15% of…
- Daily demand for a spare part is 0, 1, 2 or 3 units with probabilities 0.1, 0.3, 0.4 and 0.2. What are the mean and variance of daily…
- Urgent IT tickets arrive at an average of 3 an hour (Poisson). What is the probability that more than 2 tickets arrive in a 30-minute…
- Service times at a counter are exponential with a mean of 4 minutes. What is the probability that a service takes more than 8 minutes?
- A churn model outputs probabilities, and the team flags customers above a cut-off of 0.5. If it raises the cut-off to 0.8, what usually…
- An analyst uses 5-fold cross-validation on 1,000 rows. Which statement is correct?