A SKU is reordered 20 times a year. Management accepts at most one stockout every two years. Demand during lead time is normal with σ = 50 units. What safety stock is needed?
- A. 82 units
- B. 98 units
- C. 112 units
- D. 129 units
Correct answer: B. 98 units
Allowed stockout probability per cycle = 0.5 stockouts a year ÷ 20 cycles = 2.5%, so cycle service level = 97.5%, z = 1.96 and SS = 98. 82 units allows one stockout a year (95%); 112 uses z for 98.75% (a two-tailed slip).
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- For a raw material: weekly usage is minimum 200, normal 300 and maximum 400 units; lead time is 4–6 weeks (normal 5); reorder quantity is…
- Weekly demand is 1,000 units (σ = 100 units a week, 52 weeks). Domestic supplier A: price ₹500, freight ₹10/unit, lead time 1 week…
- Customers arrive at a branch as a Poisson process at 30 an hour, and each is independently a priority (VIP) customer with probability 0.2…
- A planner wants simple exponential smoothing to have the same average age of data as her current n-period simple moving average. Her…
- Monthly demand was 120, 130, 125 (training months 1–3) and then 140, 150, 145 (test months 4–6). A model forecast 138, 141 and 152 for…
- For stores, ad spend x (₹ lakh) has mean 10 and SD 5; sales y (₹ lakh) has mean 50 and SD 20; correlation r = 0.6. The regression of y on…