Management & CommerceHardMBA Placement · Operations · Analytics

A process has mean 50.4 and standard deviation 0.5, with specification limits of 49.0 and 52.5. The Cpk is closest to

  1. A. 0.93
  2. B. 0.47
  3. C. 1.17
  4. D. 1.40

Correct answer: A. 0.93

Cpk = min[(USL − μ)/3σ, (μ − LSL)/3σ] = min[2.1/1.5, 1.4/1.5] = 0.93. The potential capability Cp = 3.5/3 = 1.17 ignores the off-centre mean.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic