Task times on an assembly line add up to 54 minutes, with a cycle time of 9 minutes. If the line is balanced onto 7 stations, the balance efficiency is

  1. A. 85.7%
  2. B. 100%
  3. C. 77.1%
  4. D. 66.7%

Correct answer: A. 85.7%

Efficiency = total task time/(stations × cycle time) = 54/(7 × 9) = 85.7%. The minimum number of stations would be 54/9 = 6.