Management & CommerceModerateCAT · XAT
Task times on an assembly line add up to 54 minutes, with a cycle time of 9 minutes. If the line is balanced onto 7 stations, the balance efficiency is
- A. 85.7%
- B. 100%
- C. 77.1%
- D. 66.7%
Correct answer: A. 85.7%
Efficiency = total task time/(stations × cycle time) = 54/(7 × 9) = 85.7%. The minimum number of stations would be 54/9 = 6.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A machine has an availability of 90%, a performance rate of 95% and a quality rate of 98%. Its overall equipment effectiveness (OEE) is
- A regression of weekly demand on week number for weeks 1 to 5 uses demand values of 12, 15, 19, 22 and 27. The forecast for week 6 is
- A process finds 40 defects in 500 units, with each unit having 8 opportunities for a defect. The DPMO is
- A table orders(id, cust, amt) has rows (1, A, 200), (2, B, 300), (3, A, 350), (4, C, 600), (5, B, 150), (6, A, 100). The query SELECT…
- A single-server queue has arrivals of 12 an hour and a service rate of 15 an hour (M/M/1). The average time a customer waits before…
- A newsvendor buys at ₹40 and sells at ₹100, with a salvage value of ₹10 for unsold units. Demand is uniform between 200 and 500. The…