Activities (days; predecessors): A 4 (–), B 6 (–), C 5 (A), D 7 (A, B), E 3 (C, D), F 4 (D). The slack of activity C is
- A. 0 days
- B. 5 days
- C. 1 day
- D. 3 days
Correct answer: B. 5 days
Critical path is B–D–F = 17 days. ES of C = 4, and C must finish by the latest start of E (LS = 17 − 3 = 14): LS of C = 9, so slack = 9 − 4 = 5 days.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Exponential smoothing with α = 0.4 has an initial forecast of 100 for period 1. Actual demand is 110 in period 1 and 120 in period 2. The…
- A process has specification limits of 40 and 60, a mean of 52 and a standard deviation of 2.5. Cpk is closest to
- Sources S1 and S2 have supplies of 40 and 30 and destinations D1, D2 and D3 have demands of 20, 25 and 25. Unit costs are S1: 4, 6, 8; S2…
- Four workers must be assigned to four jobs, one each. Costs (rows = workers): [12, 8, 15, 10], [9, 14, 11, 7], [13, 6, 10, 12], [8, 11, 9…
- A firm has COGS of ₹90 crore and an average inventory of ₹15 crore, a receivable period of 45 days and a payable period of 40 days. The…
- Version A of a page converts 200 of 2,000 visitors (10%) and version B converts 240 of 2,000 (12%). Using a pooled two-proportion z-test…