Activities (days; predecessors): A 4 (–), B 6 (–), C 5 (A), D 7 (A, B), E 3 (C, D), F 4 (D). The slack of activity C is

  1. A. 0 days
  2. B. 5 days
  3. C. 1 day
  4. D. 3 days

Correct answer: B. 5 days

Critical path is B–D–F = 17 days. ES of C = 4, and C must finish by the latest start of E (LS = 17 − 3 = 14): LS of C = 9, so slack = 9 − 4 = 5 days.