A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table needs 5 carpentry hours and 2 finishing hours. 100 carpentry hours and 84 finishing hours are available per week. With x chairs and y tables, which is the correct LP formulation?
- A. Min 40x + 70y; 2x + 5y ≥ 100; 3x + 2y ≥ 84; x, y ≥ 0
- B. Max 40x + 70y; 2x + 3y ≤ 100; 5x + 2y ≤ 84; x, y ≥ 0
- C. Max 40x + 70y; 2x + 5y ≤ 84; 3x + 2y ≤ 100; x, y ≥ 0
- D. Max 40x + 70y; 2x + 5y ≤ 100; 3x + 2y ≤ 84; x, y ≥ 0
Correct answer: D. Max 40x + 70y; 2x + 5y ≤ 100; 3x + 2y ≤ 84; x, y ≥ 0
Each resource gives one constraint: carpentry 2x + 5y ≤ 100 and finishing 3x + 2y ≤ 84. Profit is maximised. The first distractor mixes up which coefficients belong to which product.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- Minimise C = 3x + 2y subject to x + y ≥ 8, x + 3y ≥ 12, 2x + y ≥ 10, x, y ≥ 0. What is the minimum value of C?
- In a two-variable LP solved graphically, the iso-profit line turns out to be parallel to a binding edge of the feasible region at the…
- Which statements about linear programming are correct? I. The feasible region of an LP is a convex set. II. If an optimal solution exists…
- Maximise Z = 7x + 5y subject to x + 2y ≤ 14, 3x + y ≤ 18, x − y ≤ 4, x, y ≥ 0. What is the optimal value of Z?