Management & CommerceHardBig 4 tax · CA Foundation · MBA placement pattern
In a contract where time is of the essence, the supplier delivers a week late and the buyer accepts the goods without saying anything. Later the buyer claims compensation for the delay. Which is correct?
- A. He can claim, as time was of the essence of the contract all along
- B. He cannot, as he gave no notice of his claim on accepting late
- C. He can reject the goods now and recover the full price
- D. He can claim only if the contract had a penalty clause
Correct answer: B. He cannot, as he gave no notice of his claim on accepting late
When time is essential, the promisee may avoid the contract on delay. If he instead accepts late performance, he cannot claim compensation for the delay unless he gives notice of that intention to the promisor at the time of acceptance.
More Taxation & Business Law questions
- A seller brings the agreed goods to the agreed place at the agreed time, but the buyer refuses to take delivery. What is the effect of…
- An indemnity-holder (promisee) is sued by a third party in a matter covered by the indemnity. Acting prudently and within his authority…
- A recipient takes input tax credit of ₹18,000 but has not paid the supplier when 180 days from the invoice have passed. It pays the…
- A father bought land for ₹10 lakh years ago and died; his son inherited it and has now sold it for ₹60 lakh, paying ₹1 lakh of brokerage…
- An investor bought 1,000 shares at ₹300 each and later received 1,000 bonus shares (1 : 1). She now sells the 1,000 bonus shares at ₹500…
- A company's shareholders must approve a material related-party transaction by resolution. Who may NOT vote on that resolution?