In a contract where time is of the essence, the supplier delivers a week late and the buyer accepts the goods without saying anything. Later the buyer claims compensation for the delay. Which is correct?

  1. A. He can claim, as time was of the essence of the contract all along
  2. B. He cannot, as he gave no notice of his claim on accepting late
  3. C. He can reject the goods now and recover the full price
  4. D. He can claim only if the contract had a penalty clause

Correct answer: B. He cannot, as he gave no notice of his claim on accepting late

When time is essential, the promisee may avoid the contract on delay. If he instead accepts late performance, he cannot claim compensation for the delay unless he gives notice of that intention to the promisor at the time of acceptance.