A builder contracts to construct a hall for a fixed price. Because of sharp increases in cement and steel prices, the project now costs 40% more than expected. Can the builder treat the contract as frustrated?
- A. No; mere rise in cost or hardship does not make it impossible
- B. Yes; any unforeseen event making it costlier frustrates the contract
- C. Yes, if the cost increase exceeds 25% of the contract price
- D. No, but the court must raise the contract price to cover it
Correct answer: A. No; mere rise in cost or hardship does not make it impossible
Section 56 covers performance becoming impossible or unlawful, or the commercial purpose being destroyed. Mere hardship, increased expense or market changes do not discharge a contract (e.g. Satyabrata Ghose v Mugneeram Bangur).
More Taxation & Business Law questions
- A owes B ₹5,000. B accepts ₹2,000 at A's request in full satisfaction of the whole debt, and nothing else is given. Can B later sue for…
- B rescinds a contract with A because A obtained his consent by fraud. B had earlier received ₹1 lakh from A under that contract. What must…
- A agrees to sing at B's theatre on two nights each week for three months and also agrees not to sing at any other theatre during that…
- A seller agrees to sell a horse 'at a price to be fixed by valuer X'. X refuses to value it, and the horse has not been delivered. What is…
- A buyer bought a machine described as 'new, 2025 model'. It turns out to be a reconditioned 2023 model, though it works well. Which…
- A buyer examines a second-hand car before buying it from a dealer but overlooks an obvious large dent in the door. Later she claims the…