Management & CommerceModerateCA Inter · Big 4 · MBA placement

A seller fails to deliver 1,000 units contracted at ₹50 each. On the delivery date the market price is ₹58. The buyer has not paid anything. What damages can the buyer ordinarily recover for non-delivery?

  1. A. ₹58,000
  2. B. ₹8,000
  3. C. ₹50,000
  4. D. ₹4,000

Correct answer: B. ₹8,000

Under Section 57 the usual measure is the difference between the contract price and the market price on the date fixed for delivery: (58 − 50) × 1,000 = ₹8,000, which lets the buyer buy substitutes at no extra cost.