B contracts to build a boat for C, with C paying in instalments as stages are completed; A is surety to C for B's due performance. Without A's knowledge, C pays B the last two instalments in advance. B abandons the work. Is A liable?
- A. No; prepayment impaired the surety's eventual remedy, so A is discharged
- B. Yes; a prepayment is a private matter between the creditor C and the debtor B
- C. Yes, but only for the instalments that C had not paid in advance
- D. No, but only if A had expressly forbidden C to make any prepayment
Correct answer: A. No; prepayment impaired the surety's eventual remedy, so A is discharged
Section 139: if the creditor does any act inconsistent with the surety's rights, or omits to do an act his duty requires, and the surety's eventual remedy against the debtor is impaired, the surety is discharged. Prepayment removed B's incentive to finish.
More Taxation & Business Law questions
- B borrows A's car for a weekend and promises to return it by Sunday evening. B keeps it until Tuesday; on Monday, through no fault of B…
- A buyer receives goods and neither tells the seller that he rejects them nor returns them. Four months later, after reselling part of…
- Goods are sold on three months' credit. The buyer has not taken them away, and before the credit period ends the buyer becomes insolvent…
- A cheque is presented for payment much later than a reasonable time after its issue. Before presentment, the drawee bank fails, and the…
- A company's paid-up equity capital is ₹50 crore and its free reserves are ₹30 crore. Up to what amount can it buy back its shares on the…
- A shareholder asks to inspect the minutes of the company's board meetings. Is the company obliged to allow this?