B contracts to build a boat for C, with C paying in instalments as stages are completed; A is surety to C for B's due performance. Without A's knowledge, C pays B the last two instalments in advance. B abandons the work. Is A liable?

  1. A. No; prepayment impaired the surety's eventual remedy, so A is discharged
  2. B. Yes; a prepayment is a private matter between the creditor C and the debtor B
  3. C. Yes, but only for the instalments that C had not paid in advance
  4. D. No, but only if A had expressly forbidden C to make any prepayment

Correct answer: A. No; prepayment impaired the surety's eventual remedy, so A is discharged

Section 139: if the creditor does any act inconsistent with the surety's rights, or omits to do an act his duty requires, and the surety's eventual remedy against the debtor is impaired, the surety is discharged. Prepayment removed B's incentive to finish.