Management & CommerceVery hardBusiness law · MBA placement
A contractor abandons a half-built warehouse. The owner gives the contractor written notice and then hires another builder to finish it, under the substituted-performance provision of the Specific Relief Act. What can the owner do afterwards?
- A. Recover the substitution costs, but not also seek specific performance
- B. Seek specific performance against the original contractor as well
- C. Recover nothing, since he chose to engage another builder himself
- D. Recover the costs only if the second builder was cheaper than the first
Correct answer: A. Recover the substitution costs, but not also seek specific performance
Section 20 lets the affected party get the contract performed by a third party after at least 30 days' written notice and recover the expense from the defaulter, but having done so it cannot also claim specific performance.
More Taxation & Business Law questions
- A customer accepts an online subscription contract by clicking 'I agree' and later argues it is unenforceable because nothing was signed…
- A company collects employees' personal data and decides why and how it is used; it hires a payroll firm that only processes the data on…
- An agent in Mumbai contracts in his own name to buy machines for a merchant resident in Germany, without any express term about his…
- A is appointed sole agent to sell B's tractors for a fixed term of three years. After one year, without any misconduct by A, B revokes the…
- An agent engaged to sell his principal's land secretly buys it himself through a nominee at the asking price, and resells it a month later…
- A contract for 12 monthly deliveries of steel, each paid for separately, receives one defective delivery in month 3. The buyer wants to…