A contractor abandons a half-built warehouse. The owner gives the contractor written notice and then hires another builder to finish it, under the substituted-performance provision of the Specific Relief Act. What can the owner do afterwards?

  1. A. Recover the substitution costs, but not also seek specific performance
  2. B. Seek specific performance against the original contractor as well
  3. C. Recover nothing, since he chose to engage another builder himself
  4. D. Recover the costs only if the second builder was cheaper than the first

Correct answer: A. Recover the substitution costs, but not also seek specific performance

Section 20 lets the affected party get the contract performed by a third party after at least 30 days' written notice and recover the expense from the defaulter, but having done so it cannot also claim specific performance.