A mill owner sends a broken crankshaft through a carrier to be copied. The carrier is not told that the mill is idle without it, and delays delivery. Can the owner recover the profit lost from the mill standing idle?
- A. Yes, because the idle-mill loss arose directly and naturally from the delay
- B. No, since lost profits can never be claimed for any breach of contract
- C. Yes, but only up to the amount of freight charged by the carrier
- D. No: the special loss was never communicated, so it is too remote
Correct answer: D. No: the special loss was never communicated, so it is too remote
Under Section 73 (following Hadley v Baxendale), damages cover losses arising naturally from the breach or those both parties knew, when contracting, to be likely. Special loss from circumstances not communicated is too remote.
More Taxation & Business Law questions
- A contract states that the party in breach will pay ₹5 lakh. B breaches, and A proves an actual loss of ₹2 lakh. Under Section 74 of the…
- A agrees to sell B a specific car, in a deliverable state, for ₹5 lakh, with payment and delivery next week. Before delivery the car is…
- An owner leaves his car with a mercantile agent for repairs only. The agent, acting in the ordinary course of business as a car dealer…
- A seller ships goods on credit to a buyer by rail. While the goods are in transit, the seller learns the buyer has become insolvent. Which…
- Goods are sold by sample as well as by description. The bulk matches the sample but not the description. Under the Sale of Goods Act, is…
- A bill of exchange dated 30 November 2022 is payable three months after date. Assuming no public holiday intervenes, on what date does it…