A agrees to deliver goods to B on 1 December. On 1 November A tells B he will not deliver. B may

  1. A. Wait until 1 December and only then sue
  2. B. Sue only for specific performance
  3. C. Do nothing, as no breach has occurred yet
  4. D. Treat the contract as discharged at once and sue for damages

Correct answer: D. Treat the contract as discharged at once and sue for damages

A refusal before the due date is an anticipatory breach; the promisee may rescind immediately and sue, or wait for the due date.