A contractor completes part of the work under a contract, but the owner prevents him from finishing it. The contractor may claim
- A. Nothing, as the work was not completed
- B. The entire contract price
- C. Reasonable remuneration for the work done under quantum meruit
- D. Only his cost of materials
Correct answer: C. Reasonable remuneration for the work done under quantum meruit
When one party prevents completion, the other may treat the contract as discharged and claim quantum meruit for the work done.
More Taxation & Business Law questions
- Which of the following is a valid contingent contract?
- Under the doctrine of indoor management, an outsider dealing in good faith with a company may assume internal compliance. This protection…
- Which of the following promises is enforceable even though made without consideration?
- Which of the following restraints of trade is valid under the Indian Contract Act?
- A agrees to sell his specific car to B for cash, with the property to pass at once and delivery after a week. Before delivery, the car is…
- Under Section 56 of the Indian Contract Act, which situation does NOT usually amount to frustration of a contract?