A contractor completes part of the work under a contract, but the owner prevents him from finishing it. The contractor may claim

  1. A. Nothing, as the work was not completed
  2. B. The entire contract price
  3. C. Reasonable remuneration for the work done under quantum meruit
  4. D. Only his cost of materials

Correct answer: C. Reasonable remuneration for the work done under quantum meruit

When one party prevents completion, the other may treat the contract as discharged and claim quantum meruit for the work done.