Management & CommerceHardBig 4 tax · CA Foundation · MBA placement pattern

On 1 March, A tells B he will not deliver the goods due on 1 June. What is B's position?

  1. A. B may treat the contract as ended and sue now, or wait till 1 June
  2. B. B must wait until 1 June before taking any legal action
  3. C. The contract becomes automatically void the moment A states his refusal
  4. D. B can only claim specific performance on 1 June

Correct answer: A. B may treat the contract as ended and sue now, or wait till 1 June

An anticipatory breach lets the promisee rescind and sue immediately, or keep the contract alive until the due date (Section 39); if he waits, he takes the risk of supervening events.