On 1 March, A tells B he will not deliver the goods due on 1 June. What is B's position?
- A. B may treat the contract as ended and sue now, or wait till 1 June
- B. B must wait until 1 June before taking any legal action
- C. The contract becomes automatically void the moment A states his refusal
- D. B can only claim specific performance on 1 June
Correct answer: A. B may treat the contract as ended and sue now, or wait till 1 June
An anticipatory breach lets the promisee rescind and sue immediately, or keep the contract alive until the due date (Section 39); if he waits, he takes the risk of supervening events.
More Taxation & Business Law questions
- B agreed to buy 1,000 units at ₹500 each but refused delivery on the due date, when the market price was ₹440. The seller resold a month…
- A hires a hall for a concert, but the hall is destroyed by fire, through no one's fault, before the concert date. What happens to the…
- A owes B ₹1 lakh. A, B and C agree that B will accept C as his debtor instead of A. This is:
- A publisher commissions A to write a book for a series for ₹50,000. After A has written half the book, the publisher abandons the series…
- A contract by which one party promises to save the other from loss caused by the conduct of the promisor or any other person is a contract…
- In a contract of guarantee, the three parties are: