Under the MGNREGA Schedule I, the share of works by value to be executed through Gram Panchayats is at least:
- A. 25 per cent
- B. 33 per cent
- C. 50 per cent
- D. 75 per cent
Correct answer: C. 50 per cent
At least 50% of works in terms of cost go to Gram Panchayats, the rest to other agencies; contractors are barred.
Practise more Rural Development, ARD & ESI (NABARD) questionsRural Development, ARD & ESI (NABARD): notes and key points
More Rural Development, ARD & ESI (NABARD) questions
- Under PMAY-G, 10,000 houses are sanctioned in plain areas at the unit assistance of Rs 1.20 lakh with a 60:40 Centre-State sharing. The…
- Under PMGSY (launched 25 December 2000), the original habitation population thresholds for new all-weather road connectivity were:
- A Regional Rural Bank has a paid-up capital of Rs 240 crore held as per the RRB Act 1976 pattern (Centre 50%, State 15%, sponsor bank…
- Which of the following is the sub-target within agriculture for small and marginal farmers (as % of ANBC) under the revised RBI priority…
- Total annual premium of PMSBY (Rs 20) and PMJJBY (Rs 436) is Rs 456. The life cover and accident cover under these two are, respectively:
- Which statement on Payments Banks (licensed from 2015, Nachiket Mor Committee idea) is correct?