UGC NET Paper 2 (Commerce)Hard

Budgeted overhead is Rs 120000 for 40000 machine hours. Actual hours are 38000 and actual overhead Rs 118000. The overhead is:

  1. A. Under-absorbed by 4000
  2. B. Over-absorbed by 4000
  3. C. Under-absorbed by 2000
  4. D. Over-absorbed by 2000

Correct answer: A. Under-absorbed by 4000

Rate Rs 3 per hour, absorbed = 114000 against actual 118000, so under-absorbed by 4000.