UGC NET Paper 2 (Management)Hard

In an M/M/1 queue with arrival rate 4 per hour and service rate 6 per hour, the average number in the system and utilisation are:

  1. A. 2 and 0.67
  2. B. 1.33 and 0.67
  3. C. 3 and 0.5
  4. D. 0.67 and 2

Correct answer: A. 2 and 0.67

L = lambda/(mu - lambda) = 2; rho = 4/6 = 0.67; Lq is 1.33.