Quantitative AptitudeModerateRRB NTPC · SSC CHSL

8 men can finish a job in 15 days. How many days will 10 men take at the same rate?

  1. A. 11 days
  2. B. 18 days
  3. C. 12 days
  4. D. 10 days

Correct answer: C. 12 days

Men and days are inversely proportional: 8 × 15 = 10 × d, so d = 12 days.