Quantitative AptitudeModerateRRB NTPC · SSC CHSL
8 men can finish a job in 15 days. How many days will 10 men take at the same rate?
- A. 11 days
- B. 18 days
- C. 12 days
- D. 10 days
Correct answer: C. 12 days
Men and days are inversely proportional: 8 × 15 = 10 × d, so d = 12 days.
Practise more Ratio, Proportion and Mixtures questionsRatio, Proportion and Mixtures: notes and key points
More Ratio, Proportion and Mixtures questions
- The sum of two numbers is 90 and their ratio is 7 : 8. If 6 is added to each number, the new ratio is:
- The incomes of A and B are in the ratio 7 : 5 and their expenditures are in the ratio 5 : 3. If each saves ₹1,200, A's income is:
- Alloy X has gold and silver in the ratio 2 : 3 and alloy Y in the ratio 3 : 7. In what ratio (X : Y) must they be mixed to get an alloy…
- If (a + b) : (b + c) : (c + a) = 6 : 7 : 8 and a + b + c = 21, the value of b is:
- Two numbers are in the ratio 3 : 4. If the smaller is increased by 25% and the larger is decreased by 25%, the new ratio (first : second)…
- A invests ₹12,000 for 8 months, B invests ₹9,000 for 12 months and C invests ₹6,000 for 10 months. Of a total profit of ₹66,000, B's share…