20 men working 8 hours a day complete a job in 15 days. How many days will 12 men working 10 hours a day need for the same job?

  1. A. 18 days
  2. B. 20 days
  3. C. 24 days
  4. D. 16 days

Correct answer: B. 20 days

Man-hours = 20 × 15 × 8 = 2,400. Then 12 × 10 × d = 2,400, so d = 20 days.