Quantitative AptitudeVery hardCognizant · Capgemini

A is twice as efficient as B, and B is one and a half times as efficient as C. Together they finish a job in 6 days. A alone would take:

  1. A. 12 days
  2. B. 9 days
  3. C. 11 days
  4. D. 10 days

Correct answer: C. 11 days

With B = 3 units, A = 6 and C = 2: 11 units per day. Job = 66 units, so A alone takes 66/6 = 11 days.