Quantitative AptitudeVery hardSSC CGL Tier 2 · CDS
A takes 5 days more than B and 9 days more than C to do a job alone. A and B together take as long as C alone. How long does A take alone?
- A. 10 days
- B. 6 days
- C. 12 days
- D. 15 days
Correct answer: D. 15 days
Let C = c, so A = c + 9 and B = c + 4. 1/(c + 9) + 1/(c + 4) = 1/c simplifies to c² = 36, so c = 6 and A = 15 days.
हिंदी में
A किसी कार्य को अकेले करने में B से 5 दिन अधिक और C से 9 दिन अधिक लेता है। A और B साथ मिलकर उतना ही समय लेते हैं जितना C अकेला। A अकेला कितना समय लेता है?
- A. 10 दिन
- B. 6 दिन
- C. 12 दिन
- D. 15 दिन
उत्तर: D. मान लीजिए C = c, तो A = c + 9 और B = c + 4। 1/(c + 9) + 1/(c + 4) = 1/c को सरल करने पर c² = 36, इसलिए c = 6 और A = 15 दिन।
More Time and Work questions
- A is twice as efficient as B, and B is twice as efficient as C. A finishes a job 30 days sooner than C. How long will all three take…
- Pipe A fills a tank in 12 hours and pipe B empties it in 18 hours. Starting with an empty tank, they are opened alternately for one hour…
- A works alone on day 1, A and B on day 2, A, B and C on day 3, and the pattern repeats. A, B and C alone take 30, 40 and 60 days. In how…
- Pipes A and B fill a tank in 10 and 15 hours, and pipe C drains it. With all three open, the empty tank fills in 9 hours. How long would…
- A and B together finish a job in t days. A alone would take 9 days more than t, and B alone 16 days more than t. What is t?
- A can do a job in 60 days, and A and B together in 30 days. They work together for 20 days, then B is replaced by C, who is 50% more…