3 men or 6 boys can do a job in 20 days. How long will 2 men and 4 boys take?
- A. 20 days
- B. 10 days
- C. 15 days
- D. 12 days
Correct answer: C. 15 days
1 man = 2 boys, so 2 men + 4 boys = 8 boys. 6 boys take 20 days, so 8 boys take 20 × 6/8 = 15 days.
हिंदी में
3 पुरुष या 6 लड़के किसी कार्य को 20 दिन में कर सकते हैं। 2 पुरुष और 4 लड़के कितना समय लेंगे?
- A. 20 दिन
- B. 10 दिन
- C. 15 दिन
- D. 12 दिन
उत्तर: C. 1 पुरुष = 2 लड़के, इसलिए 2 पुरुष + 4 लड़के = 8 लड़के। 6 लड़के 20 दिन लेते हैं, तो 8 लड़के 20 × 6/8 = 15 दिन लेंगे।
More Time and Work questions
- A can finish a job in 12 days and B in 18 days. They start together, but A leaves 3 days before the job is finished. In how many days is…
- Pipes A and B can fill a tank in 20 and 30 minutes, and pipe C can empty it in 15 minutes. All three are opened together, and C is closed…
- A is 60% more efficient than B. Working together they finish a job in 12 days. How long would A alone take?
- 24 men working 8 hours a day complete 2/5 of a job in 10 days. How many more men must be employed to finish the rest in 9 days, working 10…
- A can finish a job in 16 days and B in 12 days. They work on alternate days, A on the first day. In how many days is the job finished?
- A can do a job in 10 days and B in 15 days. With C's help they finish it in 4 days and are paid ₹4,500. What is C's share?