A is three times as efficient as B, and A takes 18 days less than B to finish a job alone. In how many days can they finish it working together?
- A. 6 days
- B. 7½ days
- C. 6¾ days
- D. 9 days
Correct answer: C. 6¾ days
A takes one-third of B's time: B = x, A = x/3, and x − x/3 = 18 gives x = 27, so A = 9 days. Together, 1/9 + 1/27 = 4/27, so the time is 27/4 = 6¾ days.
हिंदी में
A, B से तीन गुना कार्यकुशल है और अकेले कार्य पूरा करने में A को B से 18 दिन कम लगते हैं। साथ मिलकर कार्य करने पर वे उसे कितने दिन में पूरा करेंगे?
- A. 6 दिन
- B. 7½ दिन
- C. 6¾ दिन
- D. 9 दिन
उत्तर: C. A को B का एक-तिहाई समय लगता है: B = x, A = x/3 और x − x/3 = 18 से x = 27, अतः A = 9 दिन। साथ में 1/9 + 1/27 = 4/27, इसलिए समय 27/4 = 6¾ दिन।
More Time and Work questions
- A is 50% more efficient than B, and B is twice as efficient as C. If C alone takes 36 days to finish a job, in how many days can A and B…
- A and B together can finish a job in 10 days, and A is 1.5 times as efficient as B. A works alone for 2 days and then leaves, and B…
- A takes 6 days less than B to finish a job alone, and together they finish it in 4 days. In how many days can B alone finish it?
- 15 men working 8 hours a day complete 3/5 of a job in 12 days. How many more men, working 10 hours a day, are needed to finish the rest in…
- 8 men and 12 women can finish a job in 10 days, and 6 men and 8 women can finish it in 14 days. In how many days can 10 women alone finish…
- 4 men and 3 women can finish a job in 10 days, while 5 men alone can finish it in 12 days. In how many days can one woman alone finish it?