Quantitative AptitudeHardSSC CGL Tier 2 · IBPS PO Mains
A can do 1/3 of a job in 5 days and B can do 2/5 of the same job in 10 days. In how many days can they do the whole job together?
- A. 9¼ days
- B. 9⅜ days
- C. 9½ days
- D. 10 days
Correct answer: B. 9⅜ days
A takes 5 × 3 = 15 days and B takes 10 × 5/2 = 25 days for the whole job. Together 1/15 + 1/25 = 8/75, so the time is 75/8 = 9⅜ days.
हिंदी में
A किसी कार्य का 1/3 भाग 5 दिन में और B उसी कार्य का 2/5 भाग 10 दिन में कर सकता है। दोनों मिलकर पूरा कार्य कितने दिन में करेंगे?
- A. 9¼ दिन
- B. 9⅜ दिन
- C. 9½ दिन
- D. 10 दिन
उत्तर: B. A को पूरा कार्य करने में 5 × 3 = 15 दिन और B को 10 × 5/2 = 25 दिन लगते हैं। साथ में 1/15 + 1/25 = 8/75, अतः समय 75/8 = 9⅜ दिन।
More Time and Work questions
- A is twice as fast as B, and B is three times as fast as C. All three working together finish a job in 11 days. In how many days can C…
- A and B together can finish a job in 10 days, and A alone can finish it in 15 days. A works alone for 6 days and then leaves. How many…
- A can do a job in 12 days and B in 18 days. They work on alternate days, B starting on the first day. In how many days is the job finished?
- A, B and C can do a job alone in 10, 12 and 20 days. They work one day each in the order A, B, C, A, B, C and so on. How many days does…
- A can finish a job in 15 days and B in 20 days. They work on alternate days, A starting. On which day, and by whom, is the job completed?
- A is twice as efficient as B, and A alone finishes a job in 10 days. If they work on alternate days, B starting first, in how many days is…