Quantitative AptitudeModerateSSC CGL · RRB NTPC · IBPS PO
A alone can finish a job in 20 days and B alone in 30 days. B works every day, but A rests on every 4th day (days 4, 8, 12, …). If they start together, in how many days is the job finished?
- A. 12 days
- B. 13.8 days
- C. 14 days
- D. 13.5 days
Correct answer: B. 13.8 days
In each 4-day block A works 3 days and B works 4: 3/20 + 4/30 = 17/60. Three blocks (12 days) give 51/60. Days 13 and 14 are working days for A, so both work at 5/60 a day; day 13 reaches 56/60 and the last 4/60 takes 4/5 of day 14, so 13.8 days.
हिंदी में
A अकेला एक कार्य को 20 दिन में और B अकेला 30 दिन में पूरा कर सकता है। B प्रतिदिन कार्य करता है, परंतु A प्रत्येक चौथे दिन (4, 8, 12, … दिन) आराम करता है। यदि वे साथ शुरू करें, तो कार्य कितने दिन में पूरा होगा?
- A. 12 दिन
- B. 13.8 दिन
- C. 14 दिन
- D. 13.5 दिन
उत्तर: B. प्रत्येक 4 दिन के खंड में A 3 दिन और B 4 दिन कार्य करता है: 3/20 + 4/30 = 17/60। तीन खंड (12 दिन) में 51/60 पूरा होता है। दिन 13 और 14 में A कार्य करता है, इसलिए दोनों 5/60 प्रतिदिन करते हैं; 13वें दिन 56/60 हो जाता है और शेष 4/60 में 14वें दिन का 4/5 भाग लगता है, अतः 13.8 दिन।
More Time and Work questions
- A worker assembles 6 units on day 1 and then 2 more units each day than on the previous day (6, 8, 10, …). On which day does his total…
- A tank can be filled by pipe A in 6 hours and emptied by pipe B in 8 hours. Starting with A, the two pipes are opened alternately for one…
- A and B can do a job alone in 24 and 36 days. They work together for 6 days, after which A is replaced by C, who alone can finish the job…
- A job needs 80 worker-days. Ten workers begin it, and at the end of every 3rd day two workers leave (8 work on days 4 to 6, 6 on days 7 to…
- A, B and C can do a job alone in 18, 24 and 12 days. A starts alone; B joins him after 3 days, and 3 days after that A leaves and C joins…
- The work A does in 5 days is the same as the work B does in 4 days. Together they finish a job in 20 days. How many days will A alone take?