Quantitative AptitudeHardSSC CGL · RRB NTPC · IBPS PO
A contractor must finish a job of 330 man-hours within 3 days using 12 workers. Normal working is 8 hours a day at ₹40 an hour; any extra hour is paid at ₹60. What is the cheapest total wage bill for finishing in exactly 3 days?
- A. ₹13,200
- B. ₹19,800
- C. ₹14,880
- D. ₹14,040
Correct answer: D. ₹14,040
Normal hours available are 12 × 8 × 3 = 288, costing 288 × 40 = ₹11,520. The other 330 − 288 = 42 hours are overtime at ₹60, costing ₹2,520, so the bill is ₹14,040. ₹13,200 treats all hours as normal and ₹14,880 doubles the overtime rate.
हिंदी में
एक ठेकेदार को 12 कर्मियों से 330 मनुष्य-घंटे का कार्य 3 दिन में पूरा करना है। सामान्य कार्य प्रतिदिन 8 घंटे ₹40 प्रति घंटा की दर से है; अतिरिक्त प्रत्येक घंटे का भुगतान ₹60 है। ठीक 3 दिन में कार्य पूरा करने का न्यूनतम कुल मजदूरी व्यय कितना है?
- A. ₹13,200
- B. ₹19,800
- C. ₹14,880
- D. ₹14,040
उत्तर: D. उपलब्ध सामान्य घंटे 12 × 8 × 3 = 288 हैं, जिनका व्यय 288 × 40 = ₹11,520 है। शेष 330 − 288 = 42 घंटे ₹60 पर अतिरिक्त समय के हैं, जिनका व्यय ₹2,520 है, अतः कुल ₹14,040। ₹13,200 में सभी घंटे सामान्य मान लिए गए हैं और ₹14,880 में अतिरिक्त दर दोगुनी ले ली गई है।
More Time and Work questions
- A alone takes 12 days and B alone takes 15 days for a job. When they work together, each of them becomes 25% more efficient than when…
- A and B together can finish a job in 6 days, and A alone can finish it in 10 days. If A's speed were doubled and B's speed were halved…
- A completes 3 identical jobs in 15 days and B completes 2 such jobs in 12 days. Working together, how many days do they take to complete…
- A paints a 360 m fence from one end at 12 m a day. B starts 2 days later from the other end and paints 18 m a day. How many days after A…
- A and B together can finish a job in 12 days, and B and C together in 20 days. A is three times as fast as C. In how many days can all…
- A alone can finish a work in 12 days and B alone in 16 days. They work on alternate days, B starting on the first day. In how many days is…