Quantitative AptitudeVery hardSSC CGL Tier-2
A does 1/4 of a work in 5 days and B does 1/3 of it in 10 days. C is twice as efficient as B. In how many days will A, B and C together finish the work?
- A. 7½ days
- B. 5 days
- C. 6⅔ days
- D. 8 days
Correct answer: C. 6⅔ days
A alone: 20 days; B alone: 30 days; C (twice B) 15 days. Together 1/20 + 1/30 + 1/15 = (3 + 2 + 4)/60 = 9/60, so 60/9 = 6⅔ days.
हिंदी में
A किसी कार्य का 1/4 भाग 5 दिन में और B उसका 1/3 भाग 10 दिन में करता है। C, B से दोगुना कुशल है। A, B और C मिलकर कार्य को कितने दिन में पूरा करेंगे?
- A. 7½ दिन
- B. 5 दिन
- C. 6⅔ दिन
- D. 8 दिन
उत्तर: C. A अकेला: 20 दिन; B अकेला: 30 दिन; C (B का दोगुना) 15 दिन। साथ में 1/20 + 1/30 + 1/15 = (3 + 2 + 4)/60 = 9/60, इसलिए 60/9 = 6⅔ दिन।
More Time and Work questions
- A job needs 100 worker-days of work. 20 workers start it, and at the end of each day 2 workers leave. In how many days is the job completed?
- A is 20% more efficient than B, and B is 25% more efficient than C. Together the three finish a work in 12 days. In how many days can A…
- A pipe fills a tank in 5 hours. What part of the tank does it fill in 2 hours?
- If 4 men can paint a house in 6 days, in how many days can 3 men paint it at the same rate?
- A can do a piece of work in 15 days. What percent of the work does he complete in 6 days?
- A and B can do a work in 18 days, B and C in 24 days, and A, B and C together in 12 days. In how many days can B alone do it?