Quantitative AptitudeModerateSSC CGL · SSC CHSL
2 men can do as much work as 3 women or 4 children. If 6 men can do a work in 12 days, how long will 6 women and 8 children take to do it?
- A. 8 days
- B. 10 days
- C. 12 days
- D. 9 days
Correct answer: D. 9 days
1 woman = 2/3 man and 1 child = 1/2 man, so 6 women + 8 children = 4 + 4 = 8 men. Time = 72 man-days ÷ 8 = 9 days.
हिंदी में
2 पुरुष उतना कार्य कर सकते हैं जितना 3 महिलाएँ या 4 बच्चे। यदि 6 पुरुष किसी कार्य को 12 दिन में कर सकते हैं, तो 6 महिलाएँ और 8 बच्चे उसे कितने दिन में करेंगे?
- A. 8 दिन
- B. 10 दिन
- C. 12 दिन
- D. 9 दिन
उत्तर: D. 1 महिला = 2/3 पुरुष और 1 बच्चा = 1/2 पुरुष, इसलिए 6 महिलाएँ + 8 बच्चे = 4 + 4 = 8 पुरुष। समय = 72 आदमी-दिन ÷ 8 = 9 दिन।
More Time and Work questions
- A completes 60% of a work in 15 days and then asks B to join him. Together they finish the rest in 4 days. In how many days can B alone do…
- A job is started with 1 worker on day 1; on each later day one more worker joins (2 on day 2, 3 on day 3, and so on). One worker alone…
- A and B undertake a work for ₹7,200. A alone could do it in 12 days and B alone in 18 days. They work together for 4 days, then A leaves…
- Pipes A and B fill a tank in 30 minutes and 45 minutes. Both are opened together. After how many minutes should B be closed so that the…
- A can finish a work in 20 working days. He works every day except Sunday and starts on a Monday. On which calendar day from the start does…
- A takes 6 days more than B to do a work, and together they finish it in 4 days. How long does A alone take?