40 men can complete a work in 36 days. After 12 days, 60 more men join them. In how many more days will the remaining work be completed?
- A. 24 days
- B. 11.6 days
- C. 16 days
- D. 9.6 days
Correct answer: D. 9.6 days
Remaining work = 40 men × 24 days = 960 man-days. With 100 men: 960 ÷ 100 = 9.6 days.
हिंदी में
40 आदमी किसी कार्य को 36 दिन में पूरा कर सकते हैं। 12 दिन बाद 60 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 24 days
- B. 11.6 days
- C. 16 days
- D. 9.6 days
उत्तर: D. शेष कार्य = 40 आदमी × 24 दिन = 960 आदमी-दिन। 100 आदमियों के साथ: 960 ÷ 100 = 9.6 दिन।
More Time and Work questions
- A tap fills a tank in 6 hours. Because of a leak at the bottom, it takes 12 hours to fill the tank. The leak alone can empty the full tank…
- 60 men can complete a work in 30 days. After 4 days, 15 more men join them. In how many more days will the remaining work be completed?
- Pipes A and B can fill a tank in 15 hours and 30 hours respectively, while an outlet C can empty the full tank in 30 hours. If all three…
- A can complete a piece of work in 20 days and B in 15 days. They work together for 3 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 3:2. Together they complete a job in 18 days. How many days will B alone take?
- A can complete a piece of work in 12 days and B in 60 days. They work together for 2 days, after which A leaves. B alone will finish the…