Quantitative AptitudeModerateSSC CGL · IBPS Clerk
A and B together finish a job in 12 days; A alone takes 20 days. B alone takes:
- A. 24 days
- B. 30 days
- C. 32 days
- D. 40 days
Correct answer: B. 30 days
B's rate = 1/12 − 1/20 = (5 − 3)/60 = 1/30, so 30 days. 24 doubles the joint time and 40 doubles A's time; check: 1/20 + 1/30 = 1/12.
हिंदी में
A और B मिलकर किसी कार्य को 12 दिन में पूरा करते हैं; A अकेला 20 दिन लेता है। B अकेला कितने दिन लेगा?
- A. 24 दिन
- B. 30 दिन
- C. 32 दिन
- D. 40 दिन
उत्तर: B. B की दर = 1/12 − 1/20 = (5 − 3)/60 = 1/30, इसलिए 30 दिन। 24 संयुक्त समय का दोगुना है और 40 A के समय का दोगुना है; जाँच: 1/20 + 1/30 = 1/12।
More Time and Work questions
- A can do a work in 12 days. After working 4 days he leaves and B finishes the rest in 16 days. B alone would take:
- 12 men complete a work in 18 days. After 6 days, 4 more men join. The remaining work is finished in:
- A does one-third of a work in 6 days. He will finish the whole work in:
- One pipe fills a tank in 6 hours and another in 12 hours. Together they fill it in:
- A and B can do a work in 12 days, B and C in 15 days, and C and A in 20 days. All three together will finish it in:
- A can do a work in 20 days and B in 30 days. They begin together, but A leaves 5 days before the work is completed. The work is completed…