Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
60 men can complete a work in 20 days. After 8 days, 60 more men join them. In how many more days will the remaining work be completed?
- A. 12 days
- B. 8 days
- C. 4.5 days
- D. 6 days
Correct answer: D. 6 days
Remaining work = 60 men × 12 days = 720 man-days. With 120 men: 720 ÷ 120 = 6 days.
हिंदी में
60 आदमी किसी कार्य को 20 दिन में पूरा कर सकते हैं। 8 दिन बाद 60 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 12 days
- B. 8 days
- C. 4.5 days
- D. 6 days
उत्तर: D. शेष कार्य = 60 आदमी × 12 दिन = 720 आदमी-दिन। 120 आदमियों के साथ: 720 ÷ 120 = 6 दिन।
More Time and Work questions
- A and B can complete a work in 24 days and 12 days respectively. They work on alternate days, beginning with A. The work will be completed…
- A, B and C can complete a work alone in 8, 12 and 24 days respectively. They work together and are paid ₹3,600 in all, each in proportion…
- A tap fills a tank in 8 hours. Because of a leak at the bottom, it takes 18 hours to fill the tank. The leak alone can empty the full tank…
- A can complete a piece of work in 24 days and B in 36 days. They work together for 6 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 5:3. Together they complete a job in 12 days. How many days will B alone take?
- A, B and C can complete a work alone in 8, 24 and 30 days respectively. They work together and are paid ₹3,000 in all, each in proportion…