Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
A can complete a piece of work in 24 days and B in 30 days. They work together for 6 days, after which A leaves. B alone will finish the remaining work in:
- A. 18 days
- B. 24 days
- C. 13.2 days
- D. 16.5 days
Correct answer: D. 16.5 days
Work done together in 6 days = 6 × (1/24 + 1/30) = 0.45. Remaining = 0.55. B's time = 0.55 × 30 = 16.5 days.
हिंदी में
A किसी कार्य को 24 दिन में और B 30 दिन में पूरा कर सकता है। वे 6 दिन साथ काम करते हैं, उसके बाद A चला जाता है। शेष कार्य B अकेला कितने दिन में पूरा करेगा?
- A. 18 days
- B. 24 days
- C. 13.2 days
- D. 16.5 days
उत्तर: D. 6 दिन में साथ मिलकर किया कार्य = 6 × (1/24 + 1/30) = 0.45। शेष = 0.55। B का समय = 0.55 × 30 = 16.5 दिन।
More Time and Work questions
- 24 men can complete a work in 45 days. After 10 days, 60 more men join them. In how many more days will the remaining work be completed?
- A and B can complete a work in 15 days and 10 days respectively. They work on alternate days, beginning with A. The work will be completed…
- Pipes A and B can fill a tank in 20 hours and 40 hours respectively, while an outlet C can empty the full tank in 40 hours. If all three…
- A can complete a piece of work in 30 days and B in 60 days. They work together for 3 days, after which A leaves. B alone will finish the…
- A and B can complete a work in 12 days and 6 days respectively. They work on alternate days, beginning with A. The work will be completed…
- A tap fills a tank in 10 hours. Because of a leak at the bottom, it takes 18 hours to fill the tank. The leak alone can empty the full…