Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
20 men can complete a work in 30 days. After 6 days, 20 more men join them. In how many more days will the remaining work be completed?
- A. 24 days
- B. 12 days
- C. 14 days
- D. 10.5 days
Correct answer: B. 12 days
Remaining work = 20 men × 24 days = 480 man-days. With 40 men: 480 ÷ 40 = 12 days.
हिंदी में
20 आदमी किसी कार्य को 30 दिन में पूरा कर सकते हैं। 6 दिन बाद 20 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 24 days
- B. 12 days
- C. 14 days
- D. 10.5 days
उत्तर: B. शेष कार्य = 20 आदमी × 24 दिन = 480 आदमी-दिन। 40 आदमियों के साथ: 480 ÷ 40 = 12 दिन।
More Time and Work questions
- A, B and C can complete a work alone in 10, 12 and 24 days respectively. They work together and are paid ₹4,500 in all, each in proportion…
- A can complete a piece of work in 24 days and B in 15 days. They work together for 4 days, after which A leaves. B alone will finish the…
- A tap fills a tank in 12 hours. Because of a leak at the bottom, it takes 16 hours to fill the tank. The leak alone can empty the full…
- A can complete a piece of work in 12 days and B in 36 days. They work together for 4 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 5:3. Together they complete a job in 15 days. How many days will B alone take?
- Pipes A and B can fill a tank in 24 hours and 30 hours respectively, while an outlet C can empty the full tank in 40 hours. If all three…