Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
20 men can complete a work in 24 days. After 6 days, 10 more men join them. In how many more days will the remaining work be completed?
- A. 18 days
- B. 12 days
- C. 10.5 days
- D. 36 days
Correct answer: B. 12 days
Remaining work = 20 men × 18 days = 360 man-days. With 30 men: 360 ÷ 30 = 12 days.
हिंदी में
20 आदमी किसी कार्य को 24 दिन में पूरा कर सकते हैं। 6 दिन बाद 10 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 18 days
- B. 12 days
- C. 10.5 days
- D. 36 days
उत्तर: B. शेष कार्य = 20 आदमी × 18 दिन = 360 आदमी-दिन। 30 आदमियों के साथ: 360 ÷ 30 = 12 दिन।
More Time and Work questions
- A and B can complete a work in 30 days and 6 days respectively. They work on alternate days, beginning with A. The work will be completed…
- A and B can complete a work in 10 days and 15 days respectively. They work on alternate days, beginning with A. The work will be completed…
- Pipes A and B can fill a tank in 24 hours and 30 hours respectively, while an outlet C can empty the full tank in 30 hours. If all three…
- A can complete a piece of work in 15 days and B in 15 days. They work together for 4 days, after which A leaves. B alone will finish the…
- A tap fills a tank in 10 hours. Because of a leak at the bottom, it takes 12 hours to fill the tank. The leak alone can empty the full…
- A, B and C can complete a work alone in 8, 24 and 24 days respectively. They work together and are paid ₹1,800 in all, each in proportion…