Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
30 men can complete a work in 24 days. After 5 days, 20 more men join them. In how many more days will the remaining work be completed?
- A. 13.4 days
- B. 9.9 days
- C. 19 days
- D. 11.4 days
Correct answer: D. 11.4 days
Remaining work = 30 men × 19 days = 570 man-days. With 50 men: 570 ÷ 50 = 11.4 days.
हिंदी में
30 आदमी किसी कार्य को 24 दिन में पूरा कर सकते हैं। 5 दिन बाद 20 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 13.4 days
- B. 9.9 days
- C. 19 days
- D. 11.4 days
उत्तर: D. शेष कार्य = 30 आदमी × 19 दिन = 570 आदमी-दिन। 50 आदमियों के साथ: 570 ÷ 50 = 11.4 दिन।
More Time and Work questions
- Pipes A and B can fill a tank in 20 hours and 30 hours respectively, while an outlet C can empty the full tank in 30 hours. If all three…
- A can complete a piece of work in 20 days and B in 15 days. They work together for 4 days, after which A leaves. B alone will finish the…
- A can complete a piece of work in 12 days and B in 20 days. They work together for 6 days, after which A leaves. B alone will finish the…
- A, B and C can complete a work alone in 6, 12 and 12 days respectively. They work together and are paid ₹4,500 in all, each in proportion…
- A can complete a piece of work in 20 days and B in 10 days. They work together for 3 days, after which A leaves. B alone will finish the…
- A can complete a piece of work in 20 days and B in 20 days. They work together for 2 days, after which A leaves. B alone will finish the…