Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
45 men can complete a work in 36 days. After 12 days, 30 more men join them. In how many more days will the remaining work be completed?
- A. 14.4 days
- B. 24 days
- C. 12.9 days
- D. 16.4 days
Correct answer: A. 14.4 days
Remaining work = 45 men × 24 days = 1080 man-days. With 75 men: 1080 ÷ 75 = 14.4 days.
हिंदी में
45 आदमी किसी कार्य को 36 दिन में पूरा कर सकते हैं। 12 दिन बाद 30 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 14.4 days
- B. 24 days
- C. 12.9 days
- D. 16.4 days
उत्तर: A. शेष कार्य = 45 आदमी × 24 दिन = 1080 आदमी-दिन। 75 आदमियों के साथ: 1080 ÷ 75 = 14.4 दिन।
More Time and Work questions
- A can complete a piece of work in 20 days and B in 60 days. They work together for 2 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 3:1. Together they complete a job in 12 days. How many days will B alone take?
- A, B and C can complete a work alone in 10, 24 and 40 days respectively. They work together and are paid ₹4,500 in all, each in proportion…
- A tap fills a tank in 15 hours. Because of a leak at the bottom, it takes 20 hours to fill the tank. The leak alone can empty the full…
- Pipes A and B can fill a tank in 12 hours and 20 hours respectively, while an outlet C can empty the full tank in 120 hours. If all three…
- A can complete a piece of work in 30 days and B in 15 days. They work together for 2 days, after which A leaves. B alone will finish the…