Quantitative AptitudeModerateRRB NTPC · SSC CHSL
Working 6 hours a day, a man finishes a job in 10 days. In how many days will he finish it working 7.5 hours a day?
- A. 12.5 days
- B. 7.5 days
- C. 9 days
- D. 8 days
Correct answer: D. 8 days
Total = 60 man-hours. At 7.5 hours a day: 60 ÷ 7.5 = 8 days.
हिंदी में
प्रतिदिन 6 घंटे काम करके एक आदमी किसी कार्य को 10 दिन में पूरा करता है। प्रतिदिन 7.5 घंटे काम करने पर वह उसे कितने दिन में पूरा करेगा?
- A. 12.5 दिन
- B. 7.5 दिन
- C. 9 दिन
- D. 8 दिन
उत्तर: D. कुल = 60 आदमी-घंटे। प्रतिदिन 7.5 घंटे पर: 60 ÷ 7.5 = 8 दिन।
More Time and Work questions
- 12 carpenters working 8 hours a day make 360 chairs in 15 days. How many days will 16 carpenters working 9 hours a day take to make 540…
- A can finish a job in 10 days, and B is 25% more efficient than A. How long will B take alone?
- A tap fills 3/4 of a tank in 12 minutes. How much longer will it take to fill the rest?
- Typist A types 36 pages in 3 hours and typist B types 45 pages in 5 hours. Working together, how long will they take to type 189 pages?
- A tailor stitches 8 shirts a day and his helper 5. For an order of 146 shirts, the tailor works alone for the first 2 days and then the…
- A can do a job in 20 days and B in 30 days. They work together for 4 days. What fraction of the job is left?