Data sufficiency: decide whether the statements are sufficient to answer the question. In how many days can A alone complete a piece of work? I. A and B together complete it in 12 days. II. B alone can complete it in 20 days.
- A. Statement I alone is sufficient, but statement II alone is not
- B. Both statements together are needed
- C. Either statement alone is sufficient
- D. Even both statements together are not sufficient
Correct answer: B. Both statements together are needed
Together: 1/A = 1/12 − 1/20 = 1/30, so A takes 30 days. Alone, I has two unknowns and II says nothing about A.
Practise more Data Sufficiency and Input–Output questionsData Sufficiency and Input–Output: notes and key points
More Data Sufficiency and Input–Output questions
- Data sufficiency: decide whether the statements are sufficient to answer the question. What is the speed of a train in m/s? I. It crosses…
- Data sufficiency: decide whether the statements are sufficient to answer the question. Is the cost price of an article more than ₹500? I…
- Data sufficiency: decide whether the statements are sufficient to answer the question. Among A, B and C, who is the tallest? I. A is…
- Data sufficiency: decide whether the statements are sufficient to answer the question. What is the area of a rectangle? I. Its perimeter…
- Data sufficiency: decide whether the statements are sufficient to answer the question. How is P related to Q? I. P is the son of R. II. R…
- Data sufficiency: decide whether the statements are sufficient to answer the question. What is the value of x? I. 2x = 14. II. x/7 = 1.