A project is 4 days behind and a contract penalty applies at Rs 2.5 lakh per day of delay. Crash costs per day: task A Rs 2 lakh (up to 3 days), task B Rs 1.5 lakh (up to 2 days), task C Rs 3 lakh (up to 3 days). A, B and C are all on the critical path. What is the cheapest way to avoid all delay?

  1. A. Pay the penalty of Rs 10 lakh
  2. B. Crash A by 3 days and C by 1 day for Rs 9 lakh
  3. C. Crash B by 2 days and A by 2 days for Rs 7 lakh, saving Rs 3 lakh against the penalty
  4. D. Crash B by 2 days and C by 2 days for Rs 9 lakh

Correct answer: C. Crash B by 2 days and A by 2 days for Rs 7 lakh, saving Rs 3 lakh against the penalty

Cut the cheapest days first: B for 2 days (Rs 3 lakh) then A for 2 days (Rs 4 lakh) totals Rs 7 lakh against a Rs 10 lakh penalty. Using the costlier task C unnecessarily raises the bill.