Decision MakingVery hardXAT
A project is 4 days behind and a contract penalty applies at Rs 2.5 lakh per day of delay. Crash costs per day: task A Rs 2 lakh (up to 3 days), task B Rs 1.5 lakh (up to 2 days), task C Rs 3 lakh (up to 3 days). A, B and C are all on the critical path. What is the cheapest way to avoid all delay?
- A. Pay the penalty of Rs 10 lakh
- B. Crash A by 3 days and C by 1 day for Rs 9 lakh
- C. Crash B by 2 days and A by 2 days for Rs 7 lakh, saving Rs 3 lakh against the penalty
- D. Crash B by 2 days and C by 2 days for Rs 9 lakh
Correct answer: C. Crash B by 2 days and A by 2 days for Rs 7 lakh, saving Rs 3 lakh against the penalty
Cut the cheapest days first: B for 2 days (Rs 3 lakh) then A for 2 days (Rs 4 lakh) totals Rs 7 lakh against a Rs 10 lakh penalty. Using the costlier task C unnecessarily raises the bill.
More Decision Making (XAT) questions
- A distributor sells 5,000 units a month at Rs 90 with variable cost Rs 60 and fixed cost Rs 1 lakh. A competitor cuts price. If the…
- A publisher must print 20,000 copies of a textbook and has four quotations. Beta Prints: Rs 46 per copy with 10% off for orders above…
- A mountaineering club must pick one guide for a high-altitude trek. Nawang: highest summit 6,000 m, 7 years, first-aid certified, Hindi…
- A venture fund is choosing one start-up for a Rs 5 crore investment. CareLoop: revenue Rs 5 crore, gross margin 45%, churn 6%, founders…
- A company must pick a logistics partner for 1,200 shipments of 8 kg each over 450 km. FastTrack: Rs 1.1 per kg per 100 km plus Rs 30 per…
- Which of the following is the LEAST appropriate response when a manager discovers that a high-performing subordinate has padded a client…