A hospital needs 2,400 extra nursing hours a year. Options: one full-time nurse costing Rs 6 lakh (2,000 productive hours), overtime at Rs 375 per hour, or an agency at Rs 330 per hour. Which mix is cheapest for the 2,400 hours?

  1. A. Hire one full-timer and cover the remaining 400 hours with overtime: Rs 7.5 lakh
  2. B. Use the agency for all 2,400 hours: Rs 7.92 lakh
  3. C. Use overtime for all hours: Rs 9 lakh
  4. D. Hire two full-timers: Rs 12 lakh

Correct answer: A. Hire one full-timer and cover the remaining 400 hours with overtime: Rs 7.5 lakh

One nurse gives 2,000 hours for 6,00,000 and 400 hours of overtime cost 1,50,000, totalling Rs 7.5 lakh. The agency alone costs Rs 7.92 lakh, and a second full-timer leaves 1,600 hours idle.