Placement AptitudeHardTCS NQT · Wipro
A and B together can do a job in 10 days, B and C in 12 days, and A and C in 15 days. All three work together for 4 days, then A leaves and B and C finish the job. How many days does the job take in all?
- A. 10 days
- B. 9 days
- C. 11 days
- D. 12 days
Correct answer: A. 10 days
2(A + B + C) = 1/10 + 1/12 + 1/15 = 1/4, so A + B + C = 1/8 per day. In 4 days half the job is done; B + C (1/12 per day) needs 6 more days, so 10 days in all.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- A can finish a job in 15 days, and B is 50% more efficient than A. They work on alternate days, A on the first day. On which day is the…
- How many times between 12 noon and 12 midnight (the same day) do the hands of a clock make an angle of exactly 60°?
- When, for the first time after 9 o'clock, do the hands of a clock make an angle of exactly 30°?
- 1 January 2027 is a Friday. What day of the week is 1 January 2031?
- What is the largest number of 'Friday the 13th' dates that can occur in one calendar year?
- The sum of the first 20 terms of an arithmetic progression is 400 and the sum of its first 40 terms is 1600. What is the sum of its first…