Placement AptitudeHardTCS NQT Advanced · Capgemini
A pipe can fill a tank in 6 hours. When the tank was exactly half full a leak developed at the bottom, and the tank took 7 hours in all to fill. How long would the leak alone take to empty the full tank?
- A. 42 hours
- B. 8 hours
- C. 12 hours
- D. 24 hours
Correct answer: D. 24 hours
The first half took 3 hours, so the second half took 4 hours at net rate 1/8 per hour. 1/6 − 1/L = 1/8 gives L = 24 hours. Assuming the leak ran from the start (1/6 − 1/L = 1/7) gives 42 hours.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- If A works for 4 days, B can finish the rest of a job in 24 days. If A works for 10 days, B can finish the rest in 15 days. How many days…
- A can do a job in 12 days and B in 16 days. With the help of C, the three finish it in 4 days and are paid ₹4800 in all, shared in…
- What is the angle between the hour hand and the minute hand of a clock at 7:38?
- In a 12-hour period, how many times are the hands of a clock in a position such that, if the hour and minute hands were swapped, the…
- A clock gains 5 seconds every hour. It is set right at noon. After how long will it next show the correct time again?
- What day of the week was 2 October 1869?