A pipe can fill a tank in 6 hours. When the tank was exactly half full a leak developed at the bottom, and the tank took 7 hours in all to fill. How long would the leak alone take to empty the full tank?

  1. A. 42 hours
  2. B. 8 hours
  3. C. 12 hours
  4. D. 24 hours

Correct answer: D. 24 hours

The first half took 3 hours, so the second half took 4 hours at net rate 1/8 per hour. 1/6 − 1/L = 1/8 gives L = 24 hours. Assuming the leak ran from the start (1/6 − 1/L = 1/7) gives 42 hours.